Contract interpretationSchedule time extension analysisSchedule time extension analysis Apportionment of costsLoss of productivityDeficient designMultiple prime contract conflictsSofTurn Loss of productivityDelay and disruptionMultiple prime contract conflicts Schedule time extension analysisChange order and paymentNon-performing contractors/subs Apportionment of costsExtended overheadContract interpretation

Project ReAlignment Successes


Installation of Hydro-Electric Plant
    Project:
    Installation of Hydro-Electric Plant


    Project Size: $ 21 Million

    Participants:
      Owner - County Water Utility
      Contractor - Large General Contractor

    Total Claim Potential: $ 2 Million

    Delay to Project: one year

    Battle Costs: $ 1.25 Million


    Duration of process:
      5 Realignment Sessions

    ReAlignment Process Players:
      ReAlignment Facilitators

    Projected Resolution Costs:
      Hard Costs: $ 80 K
      Soft Costs: delay in installation of SCADA system

    Resolution Solution: $12,500

    Issue Analysis: Parties determined that plant could be installed and operated manually while they worked out the kinks in the SCADA system

<< Back to Successes
Construction Project Contract Dispute Resolution
More Info On Project Alignment     
How Can We Help You?

* Name:

* Phone:
  
* E-mail:

How did you hear about us?:

If You Used a Search Engine, Which One?:

How can we help you?


Construction Contract Delays
home   about us   services   our successes   associates   what you need   questions   podcasts   contact us
© 2008 The ReAlignment Group, Ltd.Differing site conditions
Non-performing contractors/subs