Contract interpretationSchedule time extension analysisSchedule time extension analysis Apportionment of costsLoss of productivityDeficient designMultiple prime contract conflictsSofTurn Loss of productivityDelay and disruptionMultiple prime contract conflicts Schedule time extension analysisChange order and paymentNon-performing contractors/subs Apportionment of costsExtended overheadContract interpretation

Project ReAlignment Successes


    Project: State Mental Hospital - Legal Offenders Unit

    Project Size: $ 72 Million

    Participants:
      Owner - State
      Designer - Architect
      Contractor - Large General Contractor
      1 Major Sub - Electrical

    Total Claim Potential: $ 2 to 6 Million in Claims - (Mostly unprocessed Change Orders)

    Delay to Project: Project Completed - Looking at 2 + years for litigation

    Battle Costs: $ 1.5 Million


    Scenario: Owner's Team:
    • Building too be proud of - workmanship was excellent
    • Contractor and Subs - willingness to put resources on project
    • Weather the first year - challenging
    • Lots of young talent - they stepped up to the plate - learned a lot
    • Everyone worked together - to make the process work - agreed to disagree and take care of issues at the end of the project
    • Commissioning went extremely well
    • Don't want to ruin relationships - want to work together again!

    Scenario: Contractor Team
    • Systems worked well
    • Attractive building
    • Design and Contractor Teams stayed professional during difficult times
    • People really tried to resolve issues
    • Building will serve Public well for many years to come
    • Proud of what we did

    Scenario: Major Sub
    • Worked well with General Contractor
    • Subs were cooperative with each other
    • Safety was number 1 - excellent record - even through earthquake
    • Quality building
    • Closeout went well
    • Professionalism - had heated arguments but kept on a professional level
    • Owner team worked with us to try and keep Change Order Process working - just got bogged down with all the changes
    • Reputation is important - don't want to get it hurt with Owner/Contractor

    Major Issues:
    • Contractor Team asking for 95 days delay
    • Seems to be a major difference is work performed and pricing of that work
    • Existing/Unforeseen/Differing Site Conditions
    • Limited knowledge of many electrical/mechanical systems
    • Entitlement issues - contractual

    Duration of process:
      Started process on 4/18
      Finished Change Order Negotiations - 6/20

    ReAlignment Process Players:
      ReAlignment Facilitator
      TAS - Schedule Expert / Review of Logs (RFI, FA, PCO, CO, NCR, Impact Notice,etc.) Site reports -
      IPA - Huge participation - entitlement of issues - difficult to resolve

    Resolution Solution: $ 500 K

    Issue Analysis: The contractors felt like there were a lot of site conditions that weren't called out in the contract. The other big issue was the owner felt that one of the major subs had highly inflated their prices.

<< Back to Successes
Construction Project Contract Dispute Resolution
More Info On Project Alignment     
How Can We Help You?

* Name:

* Phone:
  
* E-mail:

How did you hear about us?:

If You Used a Search Engine, Which One?:

How can we help you?


Construction Contract Delays