Project ReAlignment Successes
Project: State Mental Hospital - Legal Offenders Unit
Project Size: $ 72 Million
Participants:
Owner - State
Designer - Architect
Contractor - Large General Contractor
1 Major Sub - Electrical
Total Claim Potential: $ 2 to 6 Million in Claims - (Mostly unprocessed Change Orders)
Delay to Project: Project Completed - Looking at 2 + years for litigation
Battle Costs: $ 1.5 Million
Scenario: Owner's Team:
- Building too be proud of - workmanship was excellent
- Contractor and Subs - willingness to put resources on project
- Weather the first year - challenging
- Lots of young talent - they stepped up to the plate - learned a lot
- Everyone worked together - to make the process work - agreed to disagree and take care of issues at the end of the project
- Commissioning went extremely well
- Don't want to ruin relationships - want to work together again!
Scenario: Contractor Team
- Systems worked well
- Attractive building
- Design and Contractor Teams stayed professional during difficult times
- People really tried to resolve issues
- Building will serve Public well for many years to come
- Proud of what we did
Scenario: Major Sub
- Worked well with General Contractor
- Subs were cooperative with each other
- Safety was number 1 - excellent record - even through earthquake
- Quality building
- Closeout went well
- Professionalism - had heated arguments but kept on a professional level
- Owner team worked with us to try and keep Change Order Process working - just got bogged down with all the changes
- Reputation is important - don't want to get it hurt with Owner/Contractor
Major Issues:
- Contractor Team asking for 95 days delay
- Seems to be a major difference is work performed and pricing of that work
- Existing/Unforeseen/Differing Site Conditions
- Limited knowledge of many electrical/mechanical systems
- Entitlement issues - contractual
Duration of process:
Started process on 4/18
Finished Change Order Negotiations - 6/20
ReAlignment Process Players:
ReAlignment Facilitator
TAS - Schedule Expert / Review of Logs (RFI, FA, PCO, CO, NCR, Impact Notice,etc.) Site reports -
IPA - Huge participation - entitlement of issues - difficult to resolve
Resolution Solution: $ 500 K
Issue Analysis: The contractors felt like there were a lot of site conditions that weren't called out in the contract. The other big issue was the owner felt that one of the major subs had highly inflated their prices.
<< Back to Successes
|
|

|