Project ReAlignment Successes
Project: Infrastructure, Remodel and Classroom Additions
Project Size: $ 5 Million
Participants:
Owner - School District
Contractor - Large General Contractor
Total Claim Potential: $ 1 Million
Delay to Project: 6 months
Battle Costs: $ 600,000
Duration of process:
½ day Realignment Session
ReAlignment Process Players:
Projected Resolution Costs:
Hard Costs: $ 0
Soft Costs: one month extension of contract
Resolution Solution: $5,000
Issue Analysis: School District replaced on-site inspector, extended contract 1 month, no price change in contract