Contract interpretationSchedule time extension analysisSchedule time extension analysis Apportionment of costsLoss of productivityDeficient designMultiple prime contract conflictsSofTurn Loss of productivityDelay and disruptionMultiple prime contract conflicts Schedule time extension analysisChange order and paymentNon-performing contractors/subs Apportionment of costsExtended overheadContract interpretation

Project ReAlignment Successes


Infrastructure, Remodel and Classroom Additions
    Project: Infrastructure, Remodel and Classroom Additions

    Project Size: $ 5 Million

    Participants:
      Owner - School District
      Contractor - Large General Contractor

    Total Claim Potential: $ 1 Million

    Delay to Project: 6 months

    Battle Costs: $ 600,000


    Duration of process:
      ½ day Realignment Session

    ReAlignment Process Players:
      ReAlignment Facilitators

    Projected Resolution Costs:
      Hard Costs: $ 0
      Soft Costs: one month extension of contract

    Resolution Solution: $5,000

    Issue Analysis: School District replaced on-site inspector, extended contract 1 month, no price change in contract

<< Back to Successes
Construction Project Contract Dispute Resolution
More Info On Project Alignment     
How Can We Help You?

* Name:

* Phone:
  
* E-mail:

How did you hear about us?:

If You Used a Search Engine, Which One?:

How can we help you?


Construction Contract Delays
home   about us   services   our successes   associates   what you need   questions   podcasts   contact us
© 2008 The ReAlignment Group, Ltd.Differing site conditions
Non-performing contractors/subs