 
   
 
 
   |
Project ReAlignment Successes
High School Project
Project Size: $ 35 Million
Participants:
Owner - School District
Design Firm - Architect
Contractor - Large General Contractor
4 Major Subs - Electrical, Mechanical, Masonry and Dry Wall
Total Claim Potential: $ 7.9 Million
Delay to Project: 1 to 2 years
Battle Costs: $ 2.6 Million
Scenario: Owner's Team:
- Lack of coordination
- Communication - adversarial
- Letter writing campaign
- Not able to track construction progress
- Project behind schedule
- Poor/inexperienced/ineffective management
- Mountains of paperwork - redundant/poorly prepared
- Non review by contractor of submittals
- No schedule for submitting "submittals"
- Construction Quality Poor - non-conforming work
- Out of sequence work - doesn't know how to coordinate major trades
Scenario: Contractor Team
- No teamwork between owner and contractor
- Relationships are very strained, adversarial
- Posturing in communication
- GC/Sub motivation is waning - no payment for work performed
- Direction is not give timely - delays
- Change Order process is in the extreme - requirements, estimation, approvals - impossible to acknowledge changes
- Personal attacks on Contractor's Management
- Difficult weather
- Unforeseen conditions impacting the progress of the work - results in acceleration and trade stacking
Scenario: Major Subs Team
- Delays due to late notice and late permits
- Trade stacking, labor inefficiencies, acceleration, added supervision
- Trade coordination suffering - ability to plan long term is difficult
- No resolutions of Change Orders - GC/Subs are financing the project
- Plans/Drawings not complete - have to figure out on own
- Little or no coordination between Design and Mechanical/Electrical/Plumbing drawings
- 3 week look a head schedule is causing a lot of out of sequence work
Duration of process:
Started process on 9/17
Finished Change Order Negotiations - 12/15
Payment to the Contractors - 2/5
ReAlignment Process Players:
ReAlignment Facilitator
TAS - Schedule Expert/Helped resolve outstanding issues
IPA - Limited participation - entitlement of issues difficult to resolve
Projected Resolution Costs:
Hard Costs - $ 400 K
Soft Costs - $ 1.3 Million
ReAlignment Process: Under $ 100K
Net result: Design had a phasing process that was impossible to build. The Mechanical / Electrical became the critical path, buildings were built out of the original sequence, and decision making by the owner's team greatly impacted the project.
<< Back to Successes
|
|

|