Project ReAlign
Project ReAlignment - We Turn Projects Around
home | contact | sitemap    
Project ReAlign - We Turn Projects Around
The only system available to solve mid-project construction crises and turn the job around.
About UsServicesChange order and paymentOur SuccessesAssociatesWhat You NeedFrequently Asked QuestionsPodcasts
Contract interpretationSchedule time extension analysisSchedule time extension analysis Apportionment of costsLoss of productivityDeficient designMultiple prime contract conflictsSofTurn Loss of productivityDelay and disruptionMultiple prime contract conflicts Schedule time extension analysisChange order and paymentNon-performing contractors/subs Apportionment of costsExtended overheadContract interpretation

Project ReAlignment Successes


    High School Project

    Project Size: $ 35 Million
    Participants:
      Owner - School District
      Design Firm - Architect
      Contractor - Large General Contractor
      4 Major Subs - Electrical, Mechanical, Masonry and Dry Wall

    Total Claim Potential: $ 7.9 Million

    Delay to Project: 1 to 2 years

    Battle Costs: $ 2.6 Million


    Scenario: Owner's Team:
    • Lack of coordination
    • Communication - adversarial
    • Letter writing campaign
    • Not able to track construction progress
    • Project behind schedule
    • Poor/inexperienced/ineffective management
    • Mountains of paperwork - redundant/poorly prepared
    • Non review by contractor of submittals
    • No schedule for submitting "submittals"
    • Construction Quality Poor - non-conforming work
    • Out of sequence work - doesn't know how to coordinate major trades

    Scenario: Contractor Team
    • No teamwork between owner and contractor
    • Relationships are very strained, adversarial
    • Posturing in communication
    • GC/Sub motivation is waning - no payment for work performed
    • Direction is not give timely - delays
    • Change Order process is in the extreme - requirements, estimation, approvals - impossible to acknowledge changes
    • Personal attacks on Contractor's Management
    • Difficult weather
    • Unforeseen conditions impacting the progress of the work - results in acceleration and trade stacking

    Scenario: Major Subs Team
    • Delays due to late notice and late permits
    • Trade stacking, labor inefficiencies, acceleration, added supervision
    • Trade coordination suffering - ability to plan long term is difficult
    • No resolutions of Change Orders - GC/Subs are financing the project
    • Plans/Drawings not complete - have to figure out on own
    • Little or no coordination between Design and Mechanical/Electrical/Plumbing drawings
    • 3 week look a head schedule is causing a lot of out of sequence work

    Duration of process:
      Started process on 9/17
      Finished Change Order Negotiations - 12/15
      Payment to the Contractors - 2/5

    ReAlignment Process Players:
      ReAlignment Facilitator
      TAS - Schedule Expert/Helped resolve outstanding issues
      IPA - Limited participation - entitlement of issues difficult to resolve

    Projected Resolution Costs:
      Hard Costs - $ 400 K
      Soft Costs - $ 1.3 Million


    ReAlignment Process: Under $ 100K

    Net result: Design had a phasing process that was impossible to build. The Mechanical / Electrical became the critical path, buildings were built out of the original sequence, and decision making by the owner's team greatly impacted the project.

<< Back to Successes
Construction Project Contract Dispute Resolution
More Info On Project Alignment     
How Can We Help You?

* Name:

* Phone:
  
* E-mail:

How did you hear about us?:

If You Used a Search Engine, Which One?:

How can we help you?


Construction Contract Delays
home   about us   services   our successes   associates   what you need   questions   podcasts   contact us
© 2008 The ReAlignment Group, Ltd.Differing site conditions
Non-performing contractors/subs